A $2.17 billion data centre development at 2 Glendenning Road, Glendenning, has been approved, clearing the way for one of the larger digital infrastructure projects proposed in Western Sydney.
The State Significant Development will deliver three five-storey data centre buildings across the 10.43-hectare industrial site, with a combined gross floor area of 50,233 sqm. The approved development has a power consumption of approximately 202.4 MW and a maximum building height of 43.2 metres.
The project will be delivered in three stages, with one data centre building constructed during each stage. The exhibited scheme included three internal substations and 97 backup diesel generators to provide standby power during mains outages.
Plans also provide 165 on-site car spaces, including six accessible spaces and 12 electric vehicle charging spaces, together with landscaping and new internal access roads. The facility will operate 24 hours a day, seven days a week.
The development replaces three existing warehouse buildings on the Glendenning Road site, which adjoins Nurragingy Reserve to the east and sits within an established industrial precinct near the M7 Motorway.
The project is expected to generate around 1,076 direct construction jobs and 106 ongoing operational jobs.
Lehr Consultants International (Australia) Pty Ltd is the proponent, with Willowtree Planning leading the planning application and Greenbox Architecture responsible for the architectural design.
The application attracted two public submissions during exhibition, including an objection from Blacktown City Council. Consent was granted by the Department of Planning, Housing and Infrastructure on 14 September 2026.
For more information, search SSD-73761707 on the NSW Planning Portal.
| Application Number | SSD-73761707 |
|---|---|
| Project Title | Glendenning Road Data Centre |
| Project Status | Determined |
| Current Scheme | Approved scheme |
| Current Scheme Date | 2026-09-14 |
| Decision | Approved |
| Determination Date | 14/09/2026 |
| Project Type | Data Storage |
| Address | 2 Glendenning Road, Glendenning |
| LGA | Blacktown |
| Applicant / Developer | LEHR CONSULTANTS INTERNATIONAL (AUSTRALIA) PTY LTD |
| Site Area | 104,321 sqm (10.43 ha) |
|---|---|
| GFA | 50,233 sqm |
| Buildings | 3 |
| Storeys | 5 |
| Building Height | 45.3m |
| Parking | 165 car | 4 bike |
| Data Centre Capacity | 193.60 MW |
| Jobs | 1,076 construction / 106 operational |
| Capital Investment | $2.17 billion |
| Total Power Capacity MW | 235 MW |
|---|---|
| Potable Water Use Ml Per Year | 49 |
| Backup Generators | 97 |
| Diesel Fuel Storage Kl | 2,338 |
| Lithium Ion Battery Rooms | 6 |
| Battery Mass Kg | 2,940 |
| Internal Substations | 3 |
| Ev Charging Spaces | 12 |
| Applicant / Proponent | LEHR CONSULTANTS INTERNATIONAL (AUSTRALIA) PTY LTD |
|---|---|
| Planning / EIS Consultant | Willowtree Planning |
| Architect | Greenbox Architecture |
| Quantity Surveyor | Turner & Townsend |
| Traffic / Transport Consultant | Positive Traffic |
| Landscape Architect | Geoscapes |
| Biodiversity Consultant | Biosis |
| Acoustic Consultant | Pulse White Noise Acoustics |