$416.6m Macquarie Park Towers Proposed

A $416.6 million proposal for two residential towers reaching 34 storeys has entered public exhibition at the Morling College site in Macquarie Park.

TOGA Project Services is seeking State Significant Development approval for 550 apartments at 122 Herring Road, replacing the lower-scale development previously envisaged for the western portion of the Morling College masterplan.

The proposal comprises a 34-storey southern tower reaching 111.03 metres and a 25-storey northern tower reaching 82.5 metres, above a shared five-level basement.

Together, the towers would provide 49,710 sqm of new gross floor area, comprising 28,220 sqm in Tower 1 and 21,490 sqm in Tower 2. The residential mix includes 162 one-bedroom, 313 two-bedroom, 69 three-bedroom and six four-bedroom apartments.

Of the 550 homes, 58 would be delivered as affordable housing, with 10% of the residential GFA set aside for affordable housing for a minimum of 15 years.

The basement would accommodate 551 car spaces, including resident, visitor and car-share parking, along with 55 bicycle spaces.

Around 2,883 sqm of communal open space is proposed across the development, supplemented by 552 sqm of internal communal facilities and an outdoor terrace on Level 9 of Tower 2. The landscape scheme also includes 2,359 sqm of landscaped area and a 700 sqm publicly accessible open space between the towers.

Planning image for Residential Flat Building - 122 Herring Rd Macquarie Park at 122 Herring Road Macquarie Park.

The application represents a significant change from the existing planning approval for the site.

The broader Morling College masterplan was originally approved in 2020, with Site B providing three residential building envelopes of around 14 storeys. Amendments approved in 2023 retained three 14-storey envelopes for Site B, while allowing the separate Site A development to proceed.

Construction is already underway on Site A, where three buildings of 13 to 14 storeys will deliver 265 apartments around a central public plaza.

Under the new HDA proposal, Site B would instead accommodate the two substantially taller towers. Following early feedback from the Department of Planning, the scheme was also redistributed between the buildings: Tower 1 increased from 31 to 34 storeys, while Tower 2 was reduced from around 26–27 storeys to 23–25 storeys to improve its relationship with the neighbouring BaptistCare development and address overshadowing.

A concurrent rezoning is proposed to enable the development, increasing the maximum building height applying to Site B from 45 metres to 120 metres and increasing the site’s maximum FSR from 2.5:1 to 4:1.

The project would also complete the staged extension of the internal Waldock Road through the site and includes demolition of the existing residential college buildings within the development footprint.

The 17,154 sqm Morling College site sits within the Macquarie Park Strategic Centre, around 500 metres from Macquarie University Metro Station and Macquarie Centre.

SJB Architecture is responsible for the architectural design, with Urbis acting as planning consultant. The wider project team includes Land and Form, Beveridge Williams, AT&L and Pulse White Noise Acoustics.

For further information and exhibition documents, search SSD-108651958 on the NSW Major Projects Planning Portal.

View in Project TrackerView on Planning Portal
Project Snapshot
Project Overview
Application NumberSSD-108651958
Project TitleResidential Flat Building – 122 Herring Rd Macquarie Park
Project StatusExhibition
Current SchemeEnvironmental Impact and Rezoning Statement
Current Scheme Date2026-09-18
Project TypeHDA Housing
Address122 Herring Road Macquarie Park
LGACity of Ryde
Applicant / DeveloperTOGA Project Services Pty Ltd
Project Metrics
Site Area17,154 sqm (1.72 ha)
GFA49,710 sqm
Dwellings550
Affordable Housing58 dwellings | 10%
Buildings2
Storeys34
Building Height111.03m
Floor Space Ratio4:1
Parking551 car | 55 bike
Basement Levels5
Jobs13 operational
Capital Investment$416.6 million
Project-specific Metrics
Development Site B Area sqm6,216 sqm
Road Area sqm2,805 sqm
Total GFA For FSR sqm68,580 sqm
Tower GFA sqmTower 1: 28,220; Tower 2: 21,490
Tower Heights MTower 1: 111.03; Tower 2: 82.50
Tower StoreysTower 1: 34; Tower 2: 25
Dwelling MixOne Bedroom: 162; Two Bedroom: 313; Three Bedroom: 69; Four Bedroom: 6
Market Dwellings492
Affordable Housing Duration Years15 years
Construction Jobs By StageStage 1: 243; Stage 2: 236
Resident Car Spaces492
Visitor Car Spaces55
Car Share Spaces4
Accessible Car Spaces55
Communal Open Space sqm2,883 sqm
Internal Communal Space sqm552 sqm
Landscaped Area sqm2,359 sqm
Deep Soil sqm662 sqm
Public Open Space sqm700 sqm
Project Team
Applicant / ProponentTOGA Project Services Pty Ltd
Planning ConsultantUrbis Ltd
ArchitectSJB Architecture
Landscape ArchitectLand and Form
SurveyorBeveridge Williams
Civil / Flood EngineerAT&L
Acoustic ConsultantPulse White Noise Acoustics

Track NSW State Significant Development every week.

Explore new projects, exhibitions, determinations and other SSD status changes in the interactive Project Tracker.

More project records

Subscribe to Urban Digest Weekly

Subscribe to Urban Digest Weekly to get the latest SSD updates delivered straight to your inbox every Monday.